UQ Chemistry – CMM Centre for Microscopy and microanalysis

St Lucia, Queensland

The project involved the upgrade and expansion of an existing laboratory and Office facilities on Level 2 of the Chemistry Building at University of Queensland. The works were undertaken whilst the balance of Level 2 and building remained operational. Scope of works included a full upgrade of the Mechanical Services including the installation of 2 process chillers. Laboratory and Electrical services were expanded and upgraded to allow for the installation of new specialised equipment.

PROCUREMENT

  • Design & Construct

PROJECT SIMILARITIES

  • Operational Site
  • Scheduling of construction activities to ensure ongoing operation.
  • Sensitive Operational Issues
  • Institutional
  • Restrictive Site

Operational Issues

  • Operational facility
  • Installation of process chillers
  • Physical Containment PC2
  • Clean Rooms
  • Computer Room Air Conditioning

Project results

  • Project Cost – $894,000.
  • Duration of the Project – 6 months.
  • Nil LTI’s

Roles

  • Project Manager – Gerard Martin
  • Site Manager – Ron Ryan
  • Coordination /Administration – Stephen Cannon

UQ Qld Brain Institute (Ritchie Building) – Level 3 Office Fit out and Level 4 Small animal facility

St Lucia, Queensland

The project involved:

Level 4 – Construction of a small facility requiring the full upgrade of all building services. The external windows were all removed and replaced with new glazing to rectify a significant defect with water ingress.

Level 3 – The existing Level was gutted and a new office fit out was completed to accommodate Qld Brain Institute Researchers and staff. The works were undertaken whilst the building remained operational.

PROCUREMENT

  • Construct only

PROJECT SIMILARITIES

  • Operational Site
  • Scheduling of construction activities to ensure ongoing operation.
  • Sensitive Operational Issues
  • Institutional
  • Restrictive Site

Operational Issues

  • Operational facility
  • Physical Containment Level PC2
  • Clean rooms
  • Small animal facility

Project results

  • Project Cost – Final Cost was $ 2,000,000.
  • Duration of the Project – 5 months
  • Nil LTI’s

Roles

  • Project Manager – Gerard Martin
  • Site Manager – Simon Meredith
  • Coordination /Administration – Will Struss

UQ CMM Centre for Microscopy and Microanalysis

St Lucia, Queensland

The project involved the upgrade of all high voltage power infrastructure across the Longpocket campus. Construction of 4 substations and 2 new switchrooms. Installation of a new ring main involving the installation of conduits via directional boring and open excavation. The works were undertaken whilst the campus remained operational.

PROCUREMENT

  • Design & Construct

PROJECT SIMILARITIES

  • Operational Site
  • Scheduling of construction activities to ensure ongoing operation.
  • Sensitive Operational Issues
  • Institutional
  • Restrictive Site

Operational Issues

  • Operational facility
  • Installation of conduits using directional drilling technology to ensure protected vegetation and minimise impact to UQ grounds.
  • Detailed survey to locate and map existing services.

Project results

  • Project Cost – Final Cost was $4,500,000.
  • Duration of the Project – 14 month project.
  • Nil LTI’s

Roles

  • Project Manager – Gerard Martin
  • Site Manager – Ron Ryan
  • Coordination /Administration – Stephen Cannon

Transitional Research Institute (TRI) – Clean Room Upgrade

Woolongabba, Queensland

The project included a significant upgrade to the cleanroom HVAC system.The upgrade consisted of the installation of terminal HEPA to all cleanrooms on Level 3 of the existing building. remained operational.

PROCUREMENT

  • Design & Construct

PROJECT SIMILARITIES

  • Operational Site
  • Scheduling of construction activities to ensure ongoing operation
  • Sensitive Operational Issues
  • Restrictive Site

Operational Issues

  • Operational facility
  • Clean Room
  • Room validation in accordance with ISO14644

Project results

  • Project Cost – $270,000.
  • Duration of the Project – 4 weeks
  • Nil LTI’s

Roles

  • Project Manager – Gerard Martin
  • Site Manager – James McEwan
  • Coordination /Administration – Stephen Cannon

Peplin Operations Pty Ltd – API Southport Upgrade Project – Stage 2

Southport, Queensland

The project involved construction of a high level pharmaceutical grade clean room laboratory. The works were performed whilst the existing facility remained operational incoorporating a significant amount of hazardous area electrical installations. The project included the procurement from International supplies with high pressure on delivery to meet critical lead times.

PROCUREMENT

  • Design & Construct

PROJECT SIMILARITIES

  • Operational Site
  • Complex laboratory
  • Scheduling of construction activities to ensure ongoing operation
  • Sensitive Operational Issues
  • Restrictive Site

Operational Issues

  • Operational facility
  • Clean room construction
  • Hazardous area installation
  • Good performance, all program milestones were achieved under very challenging timeframes, all rigorous standards applied to the pharmaceutical industry were achieved.

Project results

  • Project Cost – Final Cost of all stages of work was $8,975,000. This involved building works as well as procurement & delivery of high value items.
  • Duration of the Project – 16 month project with 3 stages with all stages delivered on time.
  • Nil LTI’s

Roles

  • Project Manager – Gerard Martin
  • Site Manager – Simon Meredith
  • Coordination /Administration – Stephen Cannon

Sullivan Nicolaides Pathology – Biotech

Bowen Hills, Queensland

The project involved the relocation of Biotech laboratories from Greenslopes hospital to the new head office at Bowen Hills. The project involved the construction of a 420m2 laboratory on level B1.The management of subcontractors within an operational to ensure critical relocation dates were met was crucial to this projects success.

PROCUREMENT

  • Design & Construct

PROJECT SIMILARITIES

  • Laboratory PC2
  • Operational Sites
  • Relocation of specialist equipment & laboratory staff

Operational Issues

  • Planning refurbishment work around existing operations
  • Timing pressure against firm relocation date

Project results

  • Project Cost – Current project with expected cost of $1,460,000
  • Duration of project – Currently ahead of programme to finish mid September started in June
  • Nil LTI’s

Roles

  • Project Manager – Gerard Martin
  • Site Manager – James McEwan
  • Coordination /Administration – Stephen Cannon

University of Queensland – Australian Transformer Research Centre

Indooroopilly, Queensland

The project involved the refurbishment of an existing workshop into the new Australian Transformer Research Centre. The works involved the installation of a large transformer, fire rated separation and bunding of TX. Works were completed in an operational building at the University of Queensland Longpocket Campus.

PROCUREMENT

  • Design & Construct

PROJECT SIMILARITIES

  • Relocation of specialist equipment
  • Operational Site
  • Institutional
  • Restrictive Site

Operational Issues

  • Operational facility
  • Installation of an 8T transformer to existing building

Project results

  • Project Cost –$325,000. Only variations were client generated and fairly minor.
  • Duration of projects – Project completed over 4 months
  • Nil LTI’s

Roles

  • Project Manager – Gerard Martin 
  • Site Manager – James McEwan
  • Coordination /Administration – Stephen Cannon

Peplin Operations Pty Ltd – API Southport Upgrade Project

Southport, Queensland

The upgrade and expansion of the Peplin Operations Pty Ltd API Southport. The works involved a staged upgrade to a pharmaceutical facility. The works included the addition and upgrade of all Building Services to GMP standard. Upgrade and increase in the size of the Laboratory Area  and also the construction of an offsite facility that incorporated large scale cold room facilities and administrative offices.

PROCUREMENT

  • Managing Contractor

PROJECT SIMILARITIES

  • Operational Site
  • Complex
  • Operational Site
  • Sensitive Operational Issues
  • Restrictive Site

Operational Issues

  • Good performance, all program milestones were achieved under very challenging timeframes, all rigorous standards applied to the pharmaceutical industry were achieved.

Project results

  • Project Cost – Final Cost of all stages of work was $12,540,200. This was within the client overall Project budgets.
  • Duration of the Project – The project was staged over 20 Months. It involved a significant shutdown of the facility over the week of Easter and all program milestones were achieved at all stages of the works. Nil extensions of time were claimed or required.
  • Nil LTI’s

Roles

  • Project Manager – Gerard Martin
  • Site Manager – Simon Meredith
  • Site Engineer – Joshua Butterworth

ANNF-Q Laboratory Space Expansion – AIBN Building

University of Queensland

The refurbishment and expansion of the Clean Room laboratories on Level 2 of the AIBN Building. The works included an upgrade of the mechanical services and Laboratory gases to incorporate the relocation of a splutterer. A new process Chiller was installed in the main plant room with pipes reticulated to level 2. The works also involved the installation of 4 fume cupboards on level 4 with new PVC duct being installed up the riser thru to a new stainless steel flue on the roof. The laboratory had to remain operational throughout the duration of the works.

PROCUREMENT

  • Lump Sum

PROJECT SIMILARITIES

  • Operational Site
  • Complex
  • Sensitive Operational Issues
  • Restrictive Site

Operational Issues

  • The required Time and Cost parameters for the project were achieved.
  • Laboratory operations continued thru the construction without any incident or downtime.

Project results

  • Project Cost – Tender $605,000. Only variations were client generated and fairly minor.
  • Duration of the Project – The project was completed over a 10 week program due to the nature of the facility it was quite slow.
  • Nil LTI’s

Roles

  • Project Manager – Gerard Martin
  • Site Manager – James McEwan
  • Site Engineer – Joshua Butterworth

Idexx laboratories Upgrade Project

Brisbane, Queensland

The refurbishment and upgrade of the Idexx laboratories at Woolongabba. The works involved detailed stages so as the entire lab could remain operational through the construction period. The works included the addition and upgrade of all Laboratory and administrative functions and incorporated the construction of a mezzanine floor within the Building to increase the available GFA. The Laboratory operated 24/7 throughout the construction of the works.

PROCUREMENT

  • Design & Construct – GMP

PROJECT SIMILARITIES

  • Operational Site
  • Complex
  • Sensitive Operational Issues
  • Demolition
  • Asbestos Removal
  • Restrictive Site

Operational Issues

  • The required Time and Cost parameters for the project were achieved.
  • Business operations continued thru the construction without any incident or downtime.

Project results

  • Project Cost – Final Cost of all stages of work was $1,200,000. This was within the client overall Project budgets.
  • Duration of the project – The works were staged over 8 months. The works were planned and programmed to allow the continuous function of the Laboratory 24/7. Planned shutdown of services were undertaken to ensure the equipment and systems within the Laboratory were not compromised.
  • Nil LTI’s

Roles

  • Project Manager – Gerard Martin
  • Site Manager – James McEwan
  • Site Engineer – Joshua Butterworth

Sullivan Nicolaides Pathology

Queensland

The construction and refurbishment of Laboratories at Brisbane Mater Hospital, Wesley Hospital, Greenslopes Hospital, Gold Coast Hospital, Sunshine Coast University Hospital, Buderim Hospital, Mater Hospital Mackay, Rockhampton. Also a number of Upgrades and Refurbishments of different laboratory functions at SNP main facilities located in Taringa.

PROCUREMENT

  • Managing Contractor

PROJECT SIMILARITIES

  • Laboratories
  • Operational Sites
  • Constrained Sites
  • Complex

Operational Issues

  • Working in an existing and fully operational hospital and site.
  • Planning refurbishment work around existing operations (24/7)

Project results

  • Project Cost – Various ranging from $200,000 to $ 800,000 all delivered under Managing Contractor delivery.
  • Duration of projects – vary in accordance with scope of work. Works always required to be completed to challenging programs around the essential functions of the laboratories.
  • Nil LTI’s

Roles

  • Project Manager – Gerard Martin
  • Site Manager – Simon Meredith
  • Site Engineer – Joshua Butterworth

Australian defence Force – PC3 Lab Army malaria Institute

Gallipoli Barracks
Brisbane, Queensland

Located within the grounds of the Gallipoli Barracks this project was first of its kind for the AMI. PC3 laboratory – Containment Construction.

PROCUREMENT

  • Lump Sum

PROJECT SIMILARITIES

  • Operational Site
  • Complex

Operational Issues

  • Good performance, which surpassed the rigorous standards required by research facilities, has occurred while constructing in an operating military facility.
  • The highest quality state of the art lab was ensured by quality control procedures.

Project results

  • Project Cost – Tendered sum was $499,000 – Nil contractor variations.
  • Duration of the project – 6 month contract program completed on time.
  • Nil LTI’s

Roles

  • Project Manager – Gerard Martin
  • Site Manager – Simon Meredith

Cancer Research Centre

Brisbane, Queensland
Queensland Institute of Medical Research

Located in the grounds of the existing Royal Brisbane Hospital, the new facility includes high-tech laboratories and associated facilities.

PROCUREMENT

  • Managing Contractor

PROJECT SIMILARITIES

  • Operational Site
  • Sensitive Operational Issues
  • Demolition
  • Health / Research
  • Restrictive Site

Operational Issues

  • Located on constrained site, with functioning hospitals and including the integration of existing services with new services. Solution was to ensure methodical, well planned construction, the use of only one crane and close communication with all relevant stakeholders to achieve an incident free project.
  • Cooperative and proactive approach to working with consultants.
  • The engagement of specialist consultants regarding laboratory and related technical issues to ensure a ‘right first time’ outcome for the client.

Project results

  • Project Cost was approximately $7,500,000.
  • Completed under target / budget GCS by approx $500,000.
  • Completed one month ahead of program.
  • Nil LTI’s

Roles

  • Project Manager – Gerard Martin
  • Site Manager – Simon Meredith

Queensland Biosciences Precinct

University of Queensland
Brisbane, Queensland
University of Queensland / CSIRO

Located within the grounds of the University of Queensland’s St Lucia Campus, this project is a joint venture between the university and the CSIRO.  This is the largest of its kind in Australia housing molecular biology laboratories, shared chemistry laboratories, information science laboratories, bio-informatics laboratories, analytical chemistry and greenhouse laboratories and structural biology, development biology, synthetic chemistry and vivarium laboratories. Shared facility support, administration offices, central wash-up, workshops and stores / waste areas.  Site works include a 220 space carpark, new and upgraded services, roadworks and landscaping.

PROCUREMENT

  • Lump Sum

PROJECT SIMILARITIES

  • Operational Site
  • Complex

Operational Issues

  • Good performance, which surpassed the rigorous standards required by research facilities, has occurred while constructing in an operating campus, dealing with community relations and understanding the end user and stakeholders.

Project results

  • The highest quality state of the art labs were ensured by quality control procedures.
  • Excellent result achieved in the management of several subcontractors that encountered financial difficulties without detriment to the impact on time.

Roles

  • Project Manager – Gerard Martin
  • Area Foreman – Simon Meredith

Mr Alasdair McClintock
Director, Property & Facilities
07 3365 1111

Mater Childrens and Adults Hospital Integration

Brisbane, Queensland
Corporation of Trustees of the Sisters of Mercy Queensland

(Project experience while working for Baulderstone Hornibrook)

A complex refurbishment that included the upgrade of the accident and emergency areas of the hospital and the complete refurbishment of the CSSD, main entry, Chapel and café. All construction works were completed while the area remained fully operational.

PROCUREMENT

  • Head Contract Variation

PROJECT SIMILARITIES

  • Operational Site
  • Sensitive Operational Issues
  • Demolition
  • Health / Research
  • Restrictive Site

Operational Issues

  • Located on constrained site, with functioning hospitals and including the integration of existing services with new services.

Project results

  • Cooperative and proactive approach.
  • Open communication between client and operating staff ensured progress and successful completion.
  • Completed to target program.

Roles

  • General Foreman – Simon Meredith

Mater Children’s Hospital

Brisbane, Queensland
Corporation of Trustees of the Sisters of Mercy Queensland

(Project experience while working for Baulderstone Hornibrook)

The design included a new children’s hospital of 100 public and 40 private beds over eight levels with strong functional linkages to both the Mater Adult Public Hospital and the Mater Mother’s Hospital. A number of service collocations promoted efficiencies including emergency services, medical imaging, operating suites / day procedures and inpatient accommodation.

PROCUREMENT

  • Lump Sum

PROJECT SIMILARITIES

  • Health
  • Operational Site
  • Constrained Site
  • Complex

Operational Issues

  • Working in an existing and fully operational hospital and site.
  • Coordination of works with other contractors on site working on the surrounding infrastructure works.
  • Construction over operating access and roadways
  • Formwork system was developed to ensure construction did not affect 24 hour hospital access.

Project results

  • Completed ahead of program.
  • Success of project resulted in Baulderstone Hornibrook being awarded the partial refurbishment of Mater Adults.
  • Client commendation received.

Roles

  • Area Foreman – Simon Meredith

Mater Private Hospital Redland Collocation

Redland Bay, Queensland
Corporation of Trustees of the Sisters of Mercy Queensland

(Project experience while working for Baulderstone Hornibrook)

The hospital is a 70 bed hospital of 7,561sqm over five levels with provision for expansion. The hospital houses functions such as wards, operating theatres, kitchens, offices and is combined with a single level section that incorporates a chapel, recovery rooms, medical suites and a reception area.

PROCUREMENT

  • Construction Management

PROJECT SIMILARITIES

  • Health
  • Complex

Operational Issues

  • Environmental considerations regarding the disturbance of wildlife and protection of surrounding bushland.
  • Working within an operational campus.
  • The development and use of cardboard void formers to the basement and ground floors to compensate for the expansive clay soils.

Project results

  • Client commendation received.
  • The project was successfully constructed within the confines of a fully operational hospital site.

Roles

  • Area Foreman – Simon Meredith